News Flash

Buffalo Speedway Reconstruction

Posted on: October 9, 2019

Buffalo Speedway Reconstruction Project - 90% Design Milestone

This project is anticipated to reach the 90% design milestone in February 2020.

Key components of this project include:

  • Removal and replacement of the roadway pavement between Bissonnet Street and West Holcombe Boulevard. Construction will be approximately within the footprint of the existing roadway.

  • Installation of box culverts to improve drainage from Bissonnet Street to south of West Holcombe Boulevard to connect to the Poor Farm Ditch.

  • Replace traffic signals at Rice Boulevard, Sunset Boulevard, and University Boulevard intersection

The City will schedule a final meeting for all affected property owners along Buffalo Speedway.

========================================================================

MEETING DATE, TIME AND LOCATION

DATE:              TBD

TIME:               TBD

VENUE:            TBD

ADDRESS:       TBD

=========================================================================

For more information or to sign up for Project Alerts, visit https://westutx.gov/Buffalo.



Additional Info...
Facebook Twitter Email