Overview
Due to the age and size of this pipe, repair parts are becoming difficult to acquire. This project will replace approximately 2.400 Linear Feet of 14” cast iron pipe with a new 16” PVC line.
Preliminary engineering has been completed. A kick-off meeting was held with City staff and the City Engineer (IDS) on August 2, 2022 officially beginning the construction design phase of this project.

Proposed Project Timeline
2023
- March - 100% Design Plans Completed
- July - Bid Phase Begins
- August - Tentative Council Approval and Contract Execution
- September - Begin Construction - Approximate 9 month project duration
Project Contacts