Notice of Traffic Detour (Bridge Construction at Brays Bayou)

bigstock-Road-Closed-21711848The Harris County Flood Control District has begun construction to modify or replace three existing bridges over Brays Bayou with new higher, wider and/or longer spans that will improve the conveyance of storm water along Brays Bayou in south central Harris County. Construction begins November 19 with the closure of both the Buffalo Speedway and Ardmore Street bridges.

In August 2018, Harris County Commissioners Court awarded two construction contracts to lowest qualified bidder James Construction Group for this latest bridge work – a $6,625,343 contract for the Buffalo Speedway bridge, and a $7,889,508 contract for the Stella Link Road and Ardmore Street bridges.

Construction of all three bridges will be coordinated to reduce traffic disruptions:

  • Buffalo Speedway and Stella Link Road bridges will not be closed at the same time.
  • All lanes of the Buffalo Speedway bridge will be closed for approximately one year. The main detour through this area will be via Kirby Drive and Stella Link Road.
  • All lanes of the Ardmore Street bridge also will be closed for approximately a year and a half. The main detour through this area will be via Scott Street and State Highway 288.
  • Stella Link Road bridges will not be closed to traffic until the Buffalo Speedway bridge is reopened.
  • All Stella Link Road traffic will be shifted to one of the Stella Link Road bridges while the other is under construction.

Residents and motorists are encouraged to remain alert to changing conditions, and to pay attention to all posted lane closure and detour signs.

The upcoming bridge projects include these major components:

Buffalo Speedway bridge:

  • Demolish and replace the existing bridge with a higher, wider and longer three-span bridge
  • Replace the approaches from North and South Braeswood boulevards.
  • Add dedicated turn lanes in both directions on the bridge and on approaches to the bridge from North and South Braeswood boulevards
  • Add wider 10-foot sidewalks with shared-use bicycle paths
  • Excavate approximately 11,000 cubic yards of material underneath the bridge to match existing channel width
  • Remove and replace storm sewer systems, water line and force main

Ardmore Street bridge:

  • Demolish and replace the existing bridge with a higher and wider three-span bridge
  • Replace approaches and intersections
  • Add a dedicated U-turn lane across the bridge from South MacGregor Way to North MacGregor Way
  • Add wider 10-foot sidewalks with shared-use bicycle paths
  • Construct new channel retaining walls
  • Excavate approximately 10,000 cubic yards of material underneath the bridge to match existing channel width
  • Remove and replace storm sewer systems, water line and force main

Stella Link Road bridges:

  • Extend existing bridges 50 feet to the south
  • Replace southbound approach
  • Construct new channel retaining walls
  • Excavate approximately 20,000 cubic yards of material underneath the bridge to match existing channel width
  • Remove and replace storm sewer systems and water line

For more info https://www.hcfcd.org/press-room/current-news/2018/11/coordinated-construction-to-begin-on-buffalo-speedway-ardmore-and-stella-link-bridge-modifications-at-brays-bayou/

Facebook Twitter Google Plus Email

Other News in Community news

Christmas Tree Recycling to Begin Dec. 26

Posted on: December 13, 2018

Notice of Road Closure (Ruskin St.)

Posted on: December 3, 2018

City Flags to Fly at Half Staff

Posted on: December 1, 2018

Happy Thanksgiving

Posted on: November 21, 2018

City Offices Closed for Thanksgiving

Posted on: November 16, 2018

Buffalo Speedway Project Underway

Posted on: November 19, 2018
Councilwoman

Councilwoman Named Mayor Pro Tem

Posted on: November 15, 2018

Notice of Unclaimed Property

Posted on: October 26, 2018

We'd Love to Have Your Feedback

Posted on: September 26, 2018